Link a prime contract manually

You can manually link a prime contract in Sage Construction Management to a Sage 100 Contractor project. This is helpful if they’ve been accidentally unlinked.

Link a prime contract manually from the Prime Contract Information page

  1. Go to Projects and select the project in the Quick Select section.

  2. Select Prime Contracts in the Client Contract Admin section

  3. Select the appropriate prime contract number from the list.

  4. In the Prime Contract Information page, select Actions > Manually Link Project.

  5. Select the appropriate Sage 100 Contractor Project in the dropdown.

  6. Select Link Project.