Schedule calendars

Calendars can be established to set the work days for scheduling tasks.

  1. Log in to Sage Construction Management as an Admin.
  2. Select Settings > Feature Settings > Scheduling.
  3. In the Calendar section , select Add Calendar.
  4. Enter the Calendar Name.
  5. Select the appropriate Work Days.
  6. Optionally, enter the holiday Date and Description in the Holiday List section.
  7. Select Save & Close.