Copy a schedule

  1. Go to Projects and select the appropriate project in the Quick Select section.
  2. On the Project Home page, select Scheduling Overview or Schedules in the Scheduling section.
  3. In the Schedules (Gantt Chart) section, select Actions > Copy Schedule.
  4. Optionally, update the Project number as needed.
  5. Optionally, specify the Prime Contract number.
  6. Select the Schedule.
  7. Select Next.
  8. Select the Project number to which the schedule will be copied.
  9. Optionally, specify the Prime Contract number.

    For design-build firms, developers, and homebuilders, this field is recommended if there are going to be multiple lots or contracts.

  10. Enter the Schedule number, such as 001, and Description.
  11. Select the work Calendar which will determine the work days and holidays.
    Admins can specify the calendars in Settings > Feature Settings > Scheduling.
  12. Select Finish.